1. Modelling and Simulation of the Multi-Compartment Dry grinding ball Mills Used in Cement Industry, 2003, (TÜBİTAK-MİSAG 190-H.U. Research Fund), (co-researcher)

2. Mathematical Modelling of the High Pressure Grinding Rolls, 2002,  (TÜBİTAK-MİSAG 160), (co-researcher)

3. Determination of the Breakage Distribution Function, Used in Comminution Models, by Drop Weight Test, 2001, (H.U. Research Fund), (co-researcher)

4. Investigation of the Usage Possibility of Ankara Central Waste Water Purification Plant Filter Cake Mud in Cement Industry, 2000, (TCMA University-Industry Cooperation), (co-researcher)

5. Determination of Grinding Related Parameters of Blast Furnace Slags Used in Cement Production, 1998,  (TCMA University-Industry Cooperation), (co-researcher)

6. Determination of the Flow Conditions and Geometrical Properties at Pinched Sluices, 1998,  TÜBİTAK-YDABCAG, (co-researcher)

7. Turkish Coal Establishment Seyitömer, Orhaneli, Hüssamlar Coal Washing Plant Design, 2005

8. Performance Evaluation and Optimisation Studies at Set Italcementi İstanbul-Ambarlı Grinding&Package Plant Grinding Circuits, 2005

9. Turkish Coal Establishment Soma Coal Washing Plant Design, 2004

10. Investigation of the Çayeli Copper Corporation Flotation Circuit Performance Related to the Mineralogical Behaviour, 2004

11. Optimisation of the Ball Size Distribution at Bursa Cement Plant by Using Modelling and Simulation Techniques, 2003

12. Performance Evaluation of the Cement and Raw Material Grinding Circuits at Batı Anadolu Cement Plant, 2003

13. KÜMAŞ Magnesite Concentrator Performance Evaluation and Optimisation Studies, 2003

14. Çayeli Copper Corporation Grinding Circuits Optimisation, 2003

15. Modelling&Simulation and Performance Evaluation Studies of Clinker Grinding Circuits at Adana Cement Plant, 2002, (OYAK Adana Çement Plant)

16. Yibitaş-Lafarge Samsun, Çorum Clinker Grinding Circuits Performance Evaluation and Modelling Studies, 2002

17. Modelling and Simulation of the Raw Material and Clinker Grinding Circuits at Bolu Cement Plant, 2000, (OYAK Bolu Cement Plant)

18. Modelling and Simulation of  Clinker Grinding Circuits at Kazan Cement Plant, 2000 (OYAK Bolu Cement Plant)

19. Optimisation of  Madneuli-Georgia Copper Concentrator by Simulasyon, 2002 (KBİ)

20. Modelling and Simulation of the Raw Material and Clinker Grinding Circuits at Ankara Cement Plant, 1999, (Italcementi Set Ankara Cement Plant)

21. Crushing and Grinding Tests and Simulasyon  Studies of Kırşehir-Kaman-Çayağzı Quartz Ore,1998,  (ÇİMENTAŞ-GAZBETON)

22.Investigation of the Grinding Parameters of Steel Slags in Cement Production Process, Ereğli Iron&Steel Works Co.,2005